Planning - Settings

These settings are used for the Line Planning.

Additional Line Planning Settings
Lock Priority OrderLock Order can be used to keep the order of the selected lines in case another line is set as mainline.
Speed for Statistics

To calculate an estimated time for the duration of the survey a speed value is needed:

  • Use Average Speed from History - The average speed of the previously sailed lines will be used.
  • Use Nominal Speed Value - Enter a nominal speed on the line below this option.
Line Color Status Surveyed

This color will be used in the Navigation Display in case the color option for the "Lines from planning" is set to "Use History Color".
All lines with the status Surveyed will be displayed in the selected color.
All remaining lines will keep their original colors.